Lifted Logic Web Design in Kansas City clock location phone play check_box_outline_blank check_box chevron-down chevron-left chevron-right chevron-up facebook instagram google plus pinterest radio_button_checked radio_button_unchecked Twitter LinkedIn Youtube Mail Arrow Up Send
Where:
Junction City/Geary County
When:
2015 to 2017
Project Type:
Utility Relocation

Project Case
Study.

Northwest Interceptor Sewer Relocation

The Kansas Department of Transportation has required that all utilities be constructed outside the influence of certain interchanges

The reconstruction of the intersection at K-18 highway and US-77 Highway fell under these new regulations. Due to very large sewers laid at minimal grade, the project involved very deep tunneling, casing and excavation in order to meet the requirements of several agencies.

The Challenge

Installing a 100’ deep sewer system

In order to meet regulations of the Kansas Department of Health and Environment, minimum sewer grades for various line sizes were required to meet minimum sewer flows. This required installation of a very deep sewer using tunneling operations in areas where normal excavation equipment couldn’t be used. That depth also led to issues with groundwater and stringent EPA standards.

The Process

The Plan

We started with an overall topographical survey of the project area with the proposed interchange improvements superimposed on top of it. With this, we prepared preliminary alignments that would meet the requirements of KDOT and KDHE.

The Build

During the construction phase, groundwater was encountered that was not found during our geotechnical work. The groundwork required various means of handling to meet the discharge requirements of the EPA. The construction process involved a method that is not normally used in this area. During the construction, the contractor and our field engineers were continually engaged in addressing situations that came up during the process.

The Design

The final design yielded a construction project that would require contractors to use special equipment that would be able to tunnel through areas where the depth would exceed 80 to 100 feet. The depths would not allow the use of normal excavation equipment, so Kaw Valley Engineering provided in our design documents additional geotechnical work to define the soil, rock or shale strata that the tunneling operation would be in.

The Outcome

The relocation flowed smoothly

After some creative methods were developed, the contractor was able to successfully complete the tunneling operation at several locations. The additional capacity created by the larger pipe was more than enough to maintain the gravity flow without a major extension or pump station, and the reroute has successfully avoided influencing the interchange.